Snag lists that hold up: a site-handover checklist for SA builders

A snag list is only useful if it can be trusted later — by the client, by a body corporate, or by you if something's disputed months down the line. Here's how to run a handover process that actually holds up, not just one that ticks a box on the day.

Every builder runs some version of a snag list at handover. The problem isn't the list itself — it's what happens when a client disputes something three months later and the only record is a signed piece of paper that's gone missing, or a WhatsApp photo with no date attached to it. A snag list that can't be reconstructed isn't evidence, it's a memory.

What makes a snag list defensible

A snag record that holds up in a dispute has four things: it's dated, it's tied to a specific unit or site, it has photo evidence for each item, and it has a clear sign-off trail showing who agreed what was resolved and when. Miss any one of these and you're relying on people's memory of a walkthrough that happened months ago.

Practical checklist for a handover that holds up

Sectional title and body corporate handovers

Multi-unit projects add complexity: snags can belong to a specific unit, to common property, or to the body corporate as a whole, and disputes often surface long after individual owners move in. Keeping snag records structured by unit and by common-area category from the start avoids the scramble to work out, months later, whether a defect was ever raised and whether it was the contractor's or the body corporate's responsibility to fix.

When to call a professional

A snag list covers workmanship and finishing defects. If a walkthrough uncovers something structural, or touches electrical, roofing, waterproofing, or plumbing systems that go beyond cosmetic snagging, that item needs a qualified professional to assess and sign off — not just a note on the snag list. Treat those items separately and get them properly closed out before final handover sign-off, particularly where they could affect an insurance position later.

Why paper and WhatsApp snag lists fall apart

How SiteCheck fits

SiteCheck keeps snag items tied to a project record with dated photo evidence and sign-off tracked against each item — from the original snag through to resolution and final handover. Rather than reconstructing a timeline from scattered photos and paper after a dispute arises, the record exists as it happened, which helps if a client, body corporate, or insurer later questions what was agreed and when.

FAQ

Is a snag list legally binding?

A signed snag list is evidence of what was agreed at handover, but it's not a substitute for your contract terms. Get advice from a professional if a dispute moves beyond a normal snagging disagreement.

How long should we keep snag records after handover?

Long enough to cover any defects liability period in your contract, and any applicable legal claim period — this varies by contract and project, so check your specific terms.

Can subcontractors see the snag list, or only the main contractor?

That depends on how you set up access — SiteCheck supports role-based access so subcontractors can be shown only the items relevant to their trade, without seeing the full project record.

What if the client won't sign off on a snag list?

Record the walkthrough date, the items raised, and the client's response (even if it's a refusal to sign) — an unsigned but dated and photographed record is still far stronger evidence than nothing.