Snag lists that hold up: a site-handover checklist for SA builders
A snag list is only useful if it can be trusted later — by the client, by a body corporate, or by you if something's disputed months down the line. Here's how to run a handover process that actually holds up, not just one that ticks a box on the day.
Every builder runs some version of a snag list at handover. The problem isn't the list itself — it's what happens when a client disputes something three months later and the only record is a signed piece of paper that's gone missing, or a WhatsApp photo with no date attached to it. A snag list that can't be reconstructed isn't evidence, it's a memory.
What makes a snag list defensible
A snag record that holds up in a dispute has four things: it's dated, it's tied to a specific unit or site, it has photo evidence for each item, and it has a clear sign-off trail showing who agreed what was resolved and when. Miss any one of these and you're relying on people's memory of a walkthrough that happened months ago.
Practical checklist for a handover that holds up
- Walk the site with the client or their representative present, not alone — a snag list without the client's sign-off is your opinion, not an agreed record
- Photograph every snag item individually, not just a general sweep — vague photos are hard to defend later
- Date and timestamp every item as it's logged, not batched and entered later from memory
- Reference each snag to a specific room, unit, or location — "kitchen tap" isn't enough on a multi-unit sectional title project
- Get sign-off from the client on the snag list itself, not just a general handover certificate
- Log the resolution of each item separately, with its own date and photo — "fixed" isn't evidence, a photo of the fix is
- Get a final sign-off once all items are closed, distinct from the original snag list
- Keep the full record — original snags, resolution evidence, and both sign-offs — somewhere it can't be edited after the fact
Sectional title and body corporate handovers
Multi-unit projects add complexity: snags can belong to a specific unit, to common property, or to the body corporate as a whole, and disputes often surface long after individual owners move in. Keeping snag records structured by unit and by common-area category from the start avoids the scramble to work out, months later, whether a defect was ever raised and whether it was the contractor's or the body corporate's responsibility to fix.
When to call a professional
A snag list covers workmanship and finishing defects. If a walkthrough uncovers something structural, or touches electrical, roofing, waterproofing, or plumbing systems that go beyond cosmetic snagging, that item needs a qualified professional to assess and sign off — not just a note on the snag list. Treat those items separately and get them properly closed out before final handover sign-off, particularly where they could affect an insurance position later.
Why paper and WhatsApp snag lists fall apart
- Photos aren't reliably dated or tied to the right unit once they're mixed into a phone's camera roll
- A paper list can be lost, and there's no record of who actually signed it
- There's no clear separation between the original snag and the evidence it was fixed
- Multiple people (site supervisor, project manager, client) end up with different versions of "the list"
- Reconstructing the timeline for a dispute six months later relies entirely on memory
How SiteCheck fits
SiteCheck keeps snag items tied to a project record with dated photo evidence and sign-off tracked against each item — from the original snag through to resolution and final handover. Rather than reconstructing a timeline from scattered photos and paper after a dispute arises, the record exists as it happened, which helps if a client, body corporate, or insurer later questions what was agreed and when.
FAQ
Is a snag list legally binding?
A signed snag list is evidence of what was agreed at handover, but it's not a substitute for your contract terms. Get advice from a professional if a dispute moves beyond a normal snagging disagreement.
How long should we keep snag records after handover?
Long enough to cover any defects liability period in your contract, and any applicable legal claim period — this varies by contract and project, so check your specific terms.
Can subcontractors see the snag list, or only the main contractor?
In SiteCheck, only your own office and site staff see snags, according to their role. Subcontractor portal access covers progress claims and their status, not the snag register.
What if the client won't sign off on a snag list?
Record the walkthrough date, the items raised, and the client's response (even if it's a refusal to sign) — an unsigned but dated and photographed record is still far stronger evidence than nothing.